Roads21FB0027

CONSTRUCTION OF BYPASS ROAD, BRGY. VILLAHERMOSA, DARAGA TO SITIO NAUNTUGAN, BRGY. BARIIS, LEGAZPI CITY, ALBAY

CONSTRUCTION OF BYPASS ROAD, BRGY. VILLAHERMOSA, DARAGA TO SITIO NAUNTUGAN, BRGY. BARIIS, LEGAZPI CITY, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱48,980,581.68. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱40,613,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of drainage and flood mitigation structures along Brgy. Puro, Legazpi City, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

738 projects · ₱73.0B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS

Region VIII, Region VIII

2024₱1.3B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE

Region VIII, Region VIII

2023₱1.1B
Past target date (DPWH On-Going)
No sat.

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

Region VIII, Region VIII

2022₱511.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.8M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.5M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES(OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF ROAD,MIISI-BONGA-BUYUAN-LIDONG-DARAGA,DARAGA/

Region V, Region V

2022₱288.5M
Reported complete (100% progress, DPWH status On-Going)
View all 738 projects →

4. Implementation

Contract Amount

₱48,980,581.68

Progress

Reported complete (DPWH)

Start Date

February 12, 2021

Target End

June 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.