Roads24D00066

CONSTRUCTION OF MISSING LINKS/ NEW ROADS MAUBAN-TIGNOAN ROAD (MAUBAN SIDE), QUEZON

CONSTRUCTION OF MISSING LINKS/ NEW ROADS MAUBAN-TIGNOAN ROAD (MAUBAN SIDE), QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱28,372,063.18. Status: Past target date (DPWH On-Going). Contractor on record: DQT BUILDERS CORP FORMERLY DQT BUILDERS. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,372,063.18

Progress

Past target date (DPWH On-Going)

Start Date

May 8, 2024

Target End

August 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.