Buildings and Facilities25CC0257

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARCOS, CALUMPIT, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARCOS, CALUMPIT, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱14,478,550.30. Status: Past target date (DPWH On-Going). Contractor on record: E M CUERPO INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Pedro, Bustos, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

86 projects · ₱10.2B total · 0 flags

Other projects by this contractor

REHABILITATION OF DIKE SYSTEM ALONG SOLSONA RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT

Flood Control Management Cluster, Central Office

2017₱669.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT)

Region V, Region V

2022₱482.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY

Region VIII, Region VIII

2024₱482.2M
Past target date (DPWH On-Going)
No sat.

RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITY

Flood Control Management Cluster, Central Office

2017₱284.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2

Region VIII, Region VIII

2023₱277.7M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY

Region VIII, Region VIII

2024₱274.3M
Past target date (DPWH On-Going)
View all 86 projects →

4. Implementation

Contract Amount

₱14,478,550.30

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2025

Target End

October 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.