Rehabilitation / Major Repair of Flood Control Structure23CK0044

Rehabilitation of Existing dike along O'donnell River, Barangay Bueno Section, Left Bank, Capas, Tarlac

Rehabilitation of Existing dike along O'donnell River, Barangay Bueno Section, Left Bank, Capas, Tarlac is a DPWH-tracked public work in CAPAS (TARLAC), TARLAC, Region III. Reported contract value: ₱47,188,039.20. Status: Reported complete (DPWH). Contractor on record: RAIK CONST AND DEVELOPMENT CORP FORMERLY: RAIK CONST AND SUPPLY. Figures trace to sumbong.

CAPAS (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tarlac 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,188,039.20

Progress

Reported complete (DPWH)

Start Date

February 28, 2023

Target End

October 26, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.