Flood Control and Drainage24CC0524

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH PUMPING STATION AND FLOOD GATE AT BRGY. IBA, HAGONOY, BULACAN

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH PUMPING STATION AND FLOOD GATE AT BRGY. IBA, HAGONOY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱92,610,029.57. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Waterways and Flood Control Structure along Guiguinto River, Brgy. Malis, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱92,610,029.57

Progress

Past target date (DPWH On-Going)

Start Date

August 13, 2024

Target End

July 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.