GAA 2025 OO-225P00023

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CHICO RIVER BASIN, RIPANG SECTION,STA. 34+414 - 35+489 (R.S.), BARANGAY RIPANG, CONNER, APAYAO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CHICO RIVER BASIN, RIPANG SECTION,STA. 34+414 - 35+489 (R.S.), BARANGAY RIPANG, CONNER, APAYAO is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱95,060,496.52. Status: Past target date (DPWH On-Going). Contractor on record: RODEKOM GEN CONST AND ENT. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱6.4B total · 29 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF ROAD, KAPANGAN, BENGUET - SAN GABRIEL, LA UNIONKAPANGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱197.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLI

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETSABLAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱173.6M
Reported complete (DPWH)

Construction of Flood Control Structure along Baroro River, Barangay Bacsil, Bacnotan, LaUnion

BACNOTAN (LA UNION), LA UNION, Region I

2024₱154.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 3 (LABEY-LACAMEN SECTION, BOKOD, BENGUET), BENGUET LONE DISTRICT

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱144.8M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱95,060,496.52

Progress

Past target date (DPWH On-Going)

Start Date

April 10, 2025

Target End

January 2, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.