Buildings and Facilities19AG0036

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BAYBAY SUR, SUAL, PANGASINAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BAYBAY SUR, SUAL, PANGASINAN is a DPWH-tracked public work in Pangasinan 1st DEO, Region I. Reported contract value: ₱1,880,927.46. Status: Reported complete (DPWH). Contractor on record: HOLY FAM CONST AND SUPPLY. Figures trace to dpwh.

Pangasinan 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0020532

₱0.00 · FY2019

Released to Zamboanga Sibugay National High School (Pangi NHS) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,880,927.46

Progress

Reported complete (DPWH)

Start Date

May 16, 2019

Target End

August 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.