Construction of Flood Mitigation Structure24CF0079

Construction of Flood Mitigation Structure including Drainage System along Baca River, Barangay Mayapyap, Cabanatuan City, Nueva Ecija

Construction of Flood Mitigation Structure including Drainage System along Baca River, Barangay Mayapyap, Cabanatuan City, Nueva Ecija is a DPWH-tracked public work in CABANATUAN CITY (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱75,650,574.13. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to sumbong.

CABANATUAN CITY (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱25,354,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Casongsong River, Barangay Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0002880

₱6,100,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007112

₱1,895,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017683

₱578,300.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007113

₱175,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

495 projects · ₱7.8B total · 4 flags

4. Implementation

Contract Amount

₱75,650,574.13

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

January 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.