Construction of Flood Mitigation Structure21FA0038

Flood mitigation and rehabilitation of river control structures at the Malolos River in Malinao, Albay

Flood mitigation and rehabilitation of river control structures at the Malolos River in Malinao, Albay is a DPWH-tracked public work in ALBAY, Region V. Reported contract value: ₱19,800,000.00. Status: Reported complete (DPWH). Contractor on record: JORMAND CONST & SUPPLY. Figures trace to sumbong.

ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood mitigation and rehabilitation of river control structures at the Malolos River in Malinao, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007579

₱14,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014172

₱10,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010291

₱5,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011457

₱4,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,800,000.00

Progress

Reported complete (DPWH)

Start Date

April 19, 2022

Target End

September 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.