Buildings and Facilities18CD0254

CONSTRUCTION OF 2-STOREY, 4-CLASSROOM MALINAO PS, SAN MIGUEL, BULACAN

CONSTRUCTION OF 2-STOREY, 4-CLASSROOM MALINAO PS, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱10,675,819.77. Status: Reported complete (DPWH). Contractor on record: MANGEN TECHNO-BUILDERS INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱19,113,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Reconstruction of Road, Buga, San Miguel, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-18-0034392

₱139,000.00 · FY2018

Released to Zamboanga del Norte 3rd 201 District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱316.6M total · 0 flags

Other projects by this contractor

No sat.

BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE ULI-ULI, STA.0+168.40 TO STA.0+272.80, MANILA CITY

North Manila DEO, National Capital Region

2021₱46.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - BANK IMPROVEMENT, ESTERO DE SUNOG APOG STA. 0+821.85 TO STA. 0+927.45, MANILA CITY

North Manila DEO, National Capital Region

2019₱39.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - BANK IMPROVEMENT, ESTERO DE SUNOG APOG STA. 0+716.25 TO STA. 0+821.85, MANILA CITY

North Manila DEO, National Capital Region

2019₱39.2M
Reported complete (DPWH)
No sat.

REHABILITATION OF MULTIPURPOSE BUILDING AT BRGY. MARILAG, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2022₱19.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE COVERED COURT WITH FITNESS AND WELLNESS GYM, SPECIAL INTELLIGENCE SCHOOL, ISAFP, CAMP AGUINALDO, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2021₱19.6M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - BUILDINGS AND OTHER STRUCTURES MULTI - PURPOSE / FACILITIES - CONSTRUCTION / REHABILITATION OF MULTIPURPOSE BUILDING / DAY CARE

North Manila DEO, National Capital Region

2019₱19.3M
Reported complete (DPWH)
View all 21 projects →

4. Implementation

Contract Amount

₱10,675,819.77

Progress

Reported complete (DPWH)

Start Date

July 5, 2018

Target End

December 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.