Bridges, Roads22L00007

CONSTRUCTION OF GRAVEL ROAD - BUKIDNON - COMPOSTELA VALLEY ROAD, BRGY. NAMNAM, SAN FERNANDO, BUKIDNON - LAAK, COMPOSTELA VALLEY, PACKAGE 11, DAVAO DEL NORTE

CONSTRUCTION OF GRAVEL ROAD - BUKIDNON - COMPOSTELA VALLEY ROAD, BRGY. NAMNAM, SAN FERNANDO, BUKIDNON - LAAK, COMPOSTELA VALLEY, PACKAGE 11, DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱229,243,197.77. Status: Past target date (DPWH On-Going). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱229,243,197.77

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2022

Target End

February 10, 2023