Flood Control and Drainage19BE0132

REPAIR AND MAINTENANCE OF SISIM ABAJO FLOOD CONTROL STRUCTURE SISIM ABAJO, TUMAUINI, ISABELA

REPAIR AND MAINTENANCE OF SISIM ABAJO FLOOD CONTROL STRUCTURE SISIM ABAJO, TUMAUINI, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱13,209,430.00. Status: Reported complete (DPWH). Contractor on record: DRAGON TWELVE BUILDERS. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-19-0010322

₱-12,066,096.00 · FY2019

Released to Abra District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

448 projects · ₱5.8B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BALLACAYU FLOOD CONTROL SYSTEM

Isabela 1st DEO, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER (PACKAGE

Isabela 1st DEO, Region II

2025₱140.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE

Isabela 1st DEO, Region II

2025₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL

Isabela 1st DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)
View all 448 projects →

4. Implementation

Contract Amount

₱13,209,430.00

Progress

Reported complete (DPWH)

Start Date

December 26, 2019

Target End

July 2, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.