Roads16J00118

CONCRETING OF DARULAKRAM-SIKULLIS CIRCUMFERENTIAL ROAD, LANGUYAN, TAWI-TAWI LONE DISTRICT, STA. 0+000.00 TO STA. 1+034.33 (NET LENGTH: 1,034.33 LN.M.)

CONCRETING OF DARULAKRAM-SIKULLIS CIRCUMFERENTIAL ROAD, LANGUYAN, TAWI-TAWI LONE DISTRICT, STA. 0+000.00 TO STA. 1+034.33 (NET LENGTH: 1,034.33 LN.M.) is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱40,047,518.78. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱40,047,518.78

Progress

Reported complete (DPWH)

Start Date

August 10, 2016

Target End

January 19, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.