Rehabilitation / Major Repair of Flood Control Structure24JD0015

Rehabilitation of Flood Control Structure along Talinga River (Upstream), Talinga, Leon B. Postigo, Zamboanga del Norte

Rehabilitation of Flood Control Structure along Talinga River (Upstream), Talinga, Leon B. Postigo, Zamboanga del Norte is a DPWH-tracked public work in LEON T. POSTIGO (ZAMBOANGA DEL NORTE), ZAMBOANGA DEL NORTE, Region IX. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: ST JOSEPH CONST & TRADING. Figures trace to sumbong.

LEON T. POSTIGO (ZAMBOANGA DEL NORTE), ZAMBOANGA DEL NORTE, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Talinga River ( Upstream ) , Talinga, Leon B. Postigo, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0003725

₱2,468,519.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007625

₱1,296,481.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0003726

₱193,302.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007627

₱119,751.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱14.7M total · 0 flags

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

September 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.