Roads20EG0080

ROAD CONCRETING OF VILLION ROAD (PHASE LL), STA. 000+315 - STA. 000+502, BARANGAY SAN MANUEL, PUERTO PRINCESA CITY, PALAWAN

ROAD CONCRETING OF VILLION ROAD (PHASE LL), STA. 000+315 - STA. 000+502, BARANGAY SAN MANUEL, PUERTO PRINCESA CITY, PALAWAN is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱2,967,666.02. Status: Reported complete (DPWH). Contractor on record: UGM CONST. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,967,666.02

Progress

Reported complete (DPWH)

Start Date

May 13, 2020

Target End

June 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.