Buildings and Facilities16EF0144

CONST. OF 1-UNIT (3STY12CL) GOV. ALFREDO ABUEG SR. NATIONAL TECHNOLOGY & VOCATIONAL MEMORIAL HIGH SCHOOL, BROOKE'S POINT, PALAWAN

CONST. OF 1-UNIT (3STY12CL) GOV. ALFREDO ABUEG SR. NATIONAL TECHNOLOGY & VOCATIONAL MEMORIAL HIGH SCHOOL, BROOKE'S POINT, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱19,826,846.13. Status: Reported complete (DPWH). Contractor on record: UGM CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2016 · ₱30,000

    Possible match · score 0.74

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROI-16-0032325 · ₱179,406

    Possible match · score 0.67

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-04-25 → 2014-08-11

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 74%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Porac River, Valdez Section, Floridablanca, Pampanga 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0032325

₱179,406.00 · FY2016

Released to 00 - Don Mariano Marcos Memorial State University To cover (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,826,846.13

Progress

Reported complete (DPWH)

Start Date

November 12, 2017

Target End

May 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.