Roads23JE0069

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- PRIMARY ROADS JCT. AURORA- OZAMIS CITY RD.- K1651+385.00- K1652+569.00, MOLAVE, ZAMBOANGA DEL SUR

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- PRIMARY ROADS JCT. AURORA- OZAMIS CITY RD.- K1651+385.00- K1652+569.00, MOLAVE, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱26,052,676.74. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Brgy. Calolot, Tambulig, Zamboanga del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga del Sur 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱26,052,676.74

Progress

Reported complete (DPWH)

Start Date

April 28, 2023

Target End

October 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.