COMPLETION OF FLOOD CONTROL STRUCTURES AT STEEL SHEET PILE SECTION ALONG PALASAN RIVER,OBANDO,BULACAN (STA.2+280 - STA.2+400)
COMPLETION OF FLOOD CONTROL STRUCTURES AT STEEL SHEET PILE SECTION ALONG PALASAN RIVER,OBANDO,BULACAN (STA.2+280 - STA.2+400) is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱22,578,510.50. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR. Figures trace to dpwh.
Total Contract Cost