Roads22CD0237

CONCRETING OF BARANGAY PARADISE III FMR, BARANGAY PARADISE III, SAN JOSE DEL MONTE CITY, BULACAN

CONCRETING OF BARANGAY PARADISE III FMR, BARANGAY PARADISE III, SAN JOSE DEL MONTE CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱11,936,045.53. Status: Reported complete (DPWH). Contractor on record: SOLID PILE CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Dulong Bayan, San Jose Del Monte City, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bulacan 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

14 projects · ₱306.0M total · 0 flags

4. Implementation

Contract Amount

₱11,936,045.53

Progress

Reported complete (DPWH)

Start Date

January 11, 2023

Target End

August 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.