Roads20DJ0003

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ)-K0106+804-K0107+499, CANDELARIA, QUEZON

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ)-K0106+804-K0107+499, CANDELARIA, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱45,569,999.99. Status: Reported complete (DPWH). Contractor on record: I A BOSQUE CONST CORP. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

214 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF IYAM RIVER FLOOD CONTROL STRUCTURE, PACKAGE 5, LUCE

Quezon 2nd DEO, Region IV-A

2025₱137.1M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION OF MISSING LINKS/NEW ROADS, EXTENSION OF QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD, SAN ANTONIO SECTION, SAN

Quezon 2nd DEO, Region IV-A

2020₱125.4M
Reported complete (DPWH)

Construction of Slope Protection along Lagnas River (Upstream - Package 4), Sariaya, Quezon

SARIAYA (QUEZON), QUEZON, Region IV-A

2022₱96.5M
Reported complete (DPWH)

Construction of Slope Protection along Lagnas River (Upstream - Package 5), Sariaya, Quezon

SARIAYA (QUEZON), QUEZON, Region IV-A

2022₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY (

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, SARIAYA BYPASS ROAD-K0121+722-K0122+052, K0122+173-K0122+655, K0123+029-K0123+467

Quezon 2nd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
View all 214 projects →

4. Implementation

Contract Amount

₱45,569,999.99

Progress

Reported complete (DPWH)

Start Date

July 9, 2020

Target End

December 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.