Bridges18IB0060

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES AT DAO BRIDGE (B00521SM), ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES AT DAO BRIDGE (B00521SM), ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱4,899,872.89. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱22,230,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structures along Oras River, Oras, Eastern Samar
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-18-0022124

₱0.00 · FY2018

Released to Division of Valenzuela (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱4,899,872.89

Progress

Reported complete (DPWH)

Start Date

March 12, 2018

Target End

July 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.