Flood Control and Drainage24AA0069

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BARANGAY VISAYA, VINTAR, ILOCOS NORTE

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BARANGAY VISAYA, VINTAR, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱24,499,506.77. Status: Past target date (DPWH On-Going). Contractor on record: HEKLER BUILDERS CORP 48911. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Barangay Visaya, Vintar, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 48911

20 projects · ₱724.1M total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - IMPROVEMENT OF ROAD AT BARANGAYS LUBNAC, PARPAROROC, VISAYA, DIPILAT, DAGUPAN, AND TAMDAGAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱215.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL PROJECT ALONG BISLAK RIVER, BARANGAYTAMDAGAN, VINTAR, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱55.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION (COMPLETION) OF EVACUATION CENTER AT VETERANS MEMORIAL MEDICAL CENTER (PHASE 2), QUEZON CITY

Quezon City 1st DEO, National Capital Region

2022₱37.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF DAMAGED PROTECTION, ALONG BISLAK RIVER, BARANGAY SALSALAMAGUI, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2024₱37.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER (UPSTREAM BRIDGE), BARANGAY SAN RAMON, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱37.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURES ANDDRAINAGE SYSTEMS, CONSTRUCTION (COMPLETION) OF FLOODCONTROL STRUCTURE ALONG BISLAK RIVER IN SANJERABARANBAN, BARANGAY #16 SALSALAMAGUI, VINTAR, ILOCOSNORTE

Ilocos Norte 1st DEO, Region I

2024₱28.9M
Reported complete (DPWH)
View all 20 projects →

4. Implementation

Contract Amount

₱24,499,506.77

Progress

Past target date (DPWH On-Going)

Start Date

March 1, 2024

Target End

October 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.