Flood Control and Drainage24AA0065

CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURES ANDDRAINAGE SYSTEMS, CONSTRUCTION (COMPLETION) OF FLOODCONTROL STRUCTURE ALONG BISLAK RIVER IN SANJERABARANBAN, BARANGAY #16 SALSALAMAGUI, VINTAR, ILOCOSNORTE

CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURES ANDDRAINAGE SYSTEMS, CONSTRUCTION (COMPLETION) OF FLOODCONTROL STRUCTURE ALONG BISLAK RIVER IN SANJERABARANBAN, BARANGAY #16 SALSALAMAGUI, VINTAR, ILOCOSNORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱28,949,447.58. Status: Reported complete (DPWH). Contractor on record: HEKLER BUILDERS CORP. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction ( Completion ) of Flood Control Structure along Bislak River in Sanjera Baranban, Barangay #16 Salsalamagui, Vintar, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

22 projects · ₱778.0M total · 0 flags

Other projects by this contractor

View all 22 projects →

4. Implementation

Contract Amount

₱28,949,447.58

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

April 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.