Construction of Flood Mitigation Structure23AA0257

Construction of Flood Control Structure along Bislak River, Barangay Salsalamagui, Vintar, I Locos Norte

Construction of Flood Control Structure along Bislak River, Barangay Salsalamagui, Vintar, I Locos Norte is a DPWH-tracked public work in VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱29,399,903.60. Status: Reported complete (DPWH). Contractor on record: HEKLER BUILDERS CORP. Figures trace to sumbong.

VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Barangay Salsalamagui, Vintar, I Locos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱778.0M total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - IMPROVEMENT OF ROAD AT BARANGAYS LUBNAC, PARPAROROC, VISAYA, DIPILAT, DAGUPAN, AND TAMDAGAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱215.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL PROJECT ALONG BISLAK RIVER, BARANGAYTAMDAGAN, VINTAR, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱55.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION (COMPLETION) OF EVACUATION CENTER AT VETERANS MEMORIAL MEDICAL CENTER (PHASE 2), QUEZON CITY

Quezon City 1st DEO, National Capital Region

2022₱37.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF DAMAGED PROTECTION, ALONG BISLAK RIVER, BARANGAY SALSALAMAGUI, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2024₱37.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER (UPSTREAM BRIDGE), BARANGAY SAN RAMON, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱37.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURES ANDDRAINAGE SYSTEMS, CONSTRUCTION (COMPLETION) OF FLOODCONTROL STRUCTURE ALONG BISLAK RIVER IN SANJERABARANBAN, BARANGAY #16 SALSALAMAGUI, VINTAR, ILOCOSNORTE

Ilocos Norte 1st DEO, Region I

2024₱28.9M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱29,399,903.60

Progress

Reported complete (DPWH)

Start Date

March 29, 2023

Target End

October 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.