Unprogrammed Appropriations 202424BB0222

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINANGA, CAMALANIUGAN, CAGAYAN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINANGA, CAMALANIUGAN, CAGAYAN is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱4,814,927.67. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DECA CONST. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Zone 2, Barangay Dalla, Baggao, Cagyan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cagayan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,814,927.67

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 2, 2025

Target End

May 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.