Roads21ND0007

BRGY. LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPIT, CARMEN (LASBUENASCAR) SUSTAINABLE AGRO-FORESTRY DEVELOPMENT PROJECT, LAS NIEVES, AGUSAN DEL NORTE, PACKAGE II

BRGY. LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPIT, CARMEN (LASBUENASCAR) SUSTAINABLE AGRO-FORESTRY DEVELOPMENT PROJECT, LAS NIEVES, AGUSAN DEL NORTE, PACKAGE II is a DPWH-tracked public work in Butuan City DEO, Region XIII. Reported contract value: ₱9,797,848.29. Status: Reported complete (DPWH). Contractor on record: BN BUILDERS AND CONST SUPPLIES INC FORMERLY BN BUILDERS. Figures trace to dpwh.

Butuan City DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 69%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Brgy. Lingayao-Interim Barangay of Lawan-Lawan Road in support of Las Nieves, Buenavista, Nasipit, Carmen (LASBUENASCAR) Sustainable Agro-Forestry Development Project, Las Nieves, Agusan del Norte, Package II
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Butuan City DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

161 projects · ₱934.5M total · 0 flags

4. Implementation

Contract Amount

₱9,797,848.29

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

July 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.