Construction of Flood Mitigation Structure22CD0020

Construction of Flood Control Structure along Maasim River Diliman II Section, San Rafael, Bulacan

Construction of Flood Control Structure along Maasim River Diliman II Section, San Rafael, Bulacan is a DPWH-tracked public work in SAN RAFAEL (BULACAN), BULACAN, Region III. Reported contract value: ₱54,875,263.09. Status: Reported complete (DPWH). Contractor on record: EIRISH BUILDERS & SUPPLY INC. Figures trace to sumbong.

SAN RAFAEL (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bocaue River at Poblacion-Bambang Section, Bocaue, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002899

₱1,891,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002810

₱116,140,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱54,875,263.09

Progress

Reported complete (DPWH)

Start Date

March 7, 2022

Target End

October 9, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.