Construction of Flood Mitigation Structure23C00194

Construction of Flood Control Structure, Barangay Maguinao (BSU Section) San Rafael, Bulacan Phase II

Construction of Flood Control Structure, Barangay Maguinao (BSU Section) San Rafael, Bulacan Phase II is a DPWH-tracked public work in SAN RAFAEL (BULACAN), BULACAN, Region III. Reported contract value: ₱96,499,871.18. Status: Reported complete (DPWH). Contractor on record: EIRISH BUILDERS & SUPPLY INC. Figures trace to sumbong.

SAN RAFAEL (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱53,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. San Roque, Hagonoy, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱847.0M total · 0 flags

4. Implementation

Contract Amount

₱96,499,871.18

Progress

Reported complete (DPWH)

Start Date

June 20, 2023

Target End

March 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.