Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: Bulacan 3rd District Engineering Office awarded 26 of 26 recorded flood-control contracts (100.0%) at 99.5% or more of their Approved Budget for the Contract, versus 70.4% for flood-control contracts nationwide (29.6 percentage points higher; binomial p = 1.1e-04), across 16 contractors. Source: DPWH / Sumbong sa Pangulo contract records; each contract is listed below. This may be due to consistently competitive bidding or standard pricing practices in the district.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Bulacan 3rd District Engineering Office: contracts
26 of 26 contracts (100%) at ≥99.5% of ABC · peer baseline 70.4% · gap +29.6 pts · binomial p = 1.1e-4. Source: DPWH transparency portal and Sumbong sa Pangulo records (linked per contract).
| Contract | Title | Contractor | % of ABC | Source |
|---|---|---|---|---|
| 24C00526 | Construction of Revetment along Maguinao Creek, Barangay Maguinao, San Rafael, Bulacan | CALCON ENGINEERING | 100.01% | DPWH |
| 24C00496 | Construction of Flood Control Structure along Malangaan River (Upstream), Barangay Camachile, Doña Remedios Trinidad, Bulacan | FIVE TRAVELLERS CONST INC | 100.00% | DPWH |
| 24C00086 | Construction of Flood Control Structure along Maasim River (Package VI), Barangay Basuit, San Ildefonso, Bulacan | ADSL CONST & TRADING | 100.00% | DPWH |
| 24C00474 | Construction of Flood Mitigation Structure along Madlum River (Phase 3), Barangay Masalipit, San Miguel Bulacan | TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC | 100.00% | DPWH |
| 24C00517 | Construction of Flood Mitigation Structure including Road Dike, Malangaan Section (Downstream), Doña Remedios Trinidad, Bulacan | TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC | 100.00% | DPWH |
| 23C00188 | Construction of Flood Control Structure along Bulo River, Sta. 10 + 200 - Sta. 10 + 600, San Miguel, Bulacan | C T LEONCIO CONST & TRADING / ALLEYWAY CONST | 100.00% | DPWH |
| 23C00189 | Construction of Flood Control Structure along Bulo River, Sta. 10 + 600 - Sta. 11 + 000, San Miguel, Bulacan | ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP | 100.00% | DPWH |
| 24C00516 | Construction of Flood Mitigation Structure including Road Dike, Malangaan Section (Upstream), Doña Remedios Trinidad, Bulacan | TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC | 100.00% | DPWH |
| 23C00190 | Construction of Flood Control Structure along San Miguel River, Sta. 12+430 - Sta. 12+630, San Miguel, Bulacan | SELPHAR CONST / N B AVILA CONST | 100.00% | DPWH |
| 23C00194 | Construction of Flood Control Structure, Barangay Maguinao (BSU Section) San Rafael, Bulacan Phase II | EIRISH BUILDERS & SUPPLY INC | 100.00% | DPWH |
| 24C00471 | Construction of Flood Control Structure along San Miguel River at Marugay-rugay Bridge 2, Phase 2, Barangay Garlang, San Ildefonso, Bulacan | 729 CONST INC FORMERLY 722 CONST INC | 100.00% | DPWH |
| 24C00512 | Construction of Flood Mitigation Structure along Madlum River FSRR, Brgy. Tartaro, San Miguel, Bulacan (Phase 1) | TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC | 100.00% | DPWH |
| 24C00521 | Construction of Flood Control Structure along Maasim River, Upig Section, Brgy. Upig, San Ildefonso, Bulacan | TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC | 100.00% | DPWH |
| 23C00197 | Construction of Flood Control Structure at Galas Maasim Creek along Bypass road Phase II, Maasim, San Rafael, Bulacan | EIRISH BUILDERS & SUPPLY INC | 100.00% | DPWH |
| 23C00229 | Construction of Flood Control Structures along San Miguel River, Sta. 11 + 510 to Sta. 11 + 810, San Miguel, Bulacan | GLOBALCRETE BUILDERS INC | 100.00% | DPWH |
| 23C00227 | Construction of Flood Control Structures Along San Miguel River, Sta. 10 + 910 to Sta. 11 + 210, San Miguel Bulacan | MRRM TRADING & CONST | 100.00% | DPWH |
| 23C00191 | Construction of Flood Control Structure Mag-asawang Sapa Creek, San Ildefonso, Bulacan Phase 2 | M3 KONSTRACT CORP FORMERLY:MARGARITA CONST | 100.00% | DPWH |
| 23C00198 | Construction of Flood Control Structure along Mag-Asawang Sapa Creek Phase 3, San lldefonso, Bulacan | M3 KONSTRACT CORP FORMERLY:MARGARITA CONST | 100.00% | DPWH |
| 23C00233 | Construction of Flood Control Structure along Maasim River, Sta. 8+400 - Sta. 8+705, Brgy. Upig, San Ildefonso, Bulacan | GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC | 100.00% | DPWH |
| 23C00248 | Construction of Flood Control Structures along San Miguel River, Sta. 00+550-Sta. 00+912 (Downstream), Brgy. Batasan Bata, San Miguel, Bulacan | LE BRON CONST / OLYMPUS MINING AND BUILDERS GROUP PHILS CORP FORMERLY: OLYMPUS BUILDERS AND MINING CORP | 100.00% | DPWH |
| 23C00196 | Construction of Flood Control Structure at Galas Maasim Creek along Bypass road Phase I, Maasim, San Rafael, Bulacan | EIRISH BUILDERS & SUPPLY INC | 100.00% | DPWH |
| 23C00247 | Construction of Flood Control Structures along San Miguel River, Sta. 00+210-Sta. 00+550 (Upstream), Brgy. Batasan Bata, San Miguel, Bulacan | LE BRON CONST / OLYMPUS MINING AND BUILDERS GROUP PHILS CORP FORMERLY: OLYMPUS BUILDERS AND MINING CORP | 100.00% | DPWH |
| 24C00494 | Construction of Flood Control Structure along Balaong River (Purok 1 Section, Upstream), Barangay Tartaro, San Miguel, Bulacan | C & F CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23C00228 | Construction of Flood Control Structures along San Miguel River, Sta. 11 + 210 to Sta. 11 + 510, San Miguel, Bulacan | FLORDES CONST & TRADING CORP FORMERLY FLO | 100.00% | DPWH |
| 23C00328 | Construction of Flood Control Structure Along Maasim River, Bgy Maasim, San Rafael, Bulacan | EIRISH BUILDERS & SUPPLY INC | 100.00% | DPWH |
| 23C00187 | Construction of Flood Control Structure along Angat River, San Rafael, Bulacan | GLOBALCRETE BUILDERS INC | 99.99% | DPWH |
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Completion schedule is shown for project and contractor flags only.
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Implementing office awards near-ABC contracts far more often than the flood-control baseline
{
"office": "Bulacan 3rd District Engineering Office",
"nearAbc": 26,
"trigger": "office_pattern_aggregate",
"officeId": "68e75fe4-48cb-5d80-a0e2-faabd693a4c6",
"threshold": 0.995,
"binomialTailP": 0.00010889785845247376,
"nearAbcRatePct": 100,
"totalContracts": 26,
"baselineRatePct": 70.4,
"excessPctPoints": 29.6,
"expectedNearAbc": 18.3,
"baselineDefinition": "share of all Sumbong flood-control contracts awarded at ≥99.5% of ABC"
}Source documents
Possible Innocent Explanations
- This may be due to consistently competitive bidding or standard pricing practices in the district.