Roads16N00018

CONSTRUCTION OF BUTUAN CITY BY-PASS ROAD, (BONBON-BANCASI AIRPORT SECTION AND LEMON - NRJ - ANTONAGLON SECTION), BUTUAN CITY

CONSTRUCTION OF BUTUAN CITY BY-PASS ROAD, (BONBON-BANCASI AIRPORT SECTION AND LEMON - NRJ - ANTONAGLON SECTION), BUTUAN CITY is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱119,797,982.36. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱119,797,982.36

Progress

Reported complete (DPWH)

Start Date

September 15, 2016

Target End

August 10, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.