Construction of Slope Protection Structure24CJ0007

Construction of Slope Protection Structure along Tarlac River (Left Dike), Brillante-Aduas Section, Package J, Paniqui, Tarlac

Construction of Slope Protection Structure along Tarlac River (Left Dike), Brillante-Aduas Section, Package J, Paniqui, Tarlac is a DPWH-tracked public work in PANIQUI (TARLAC), TARLAC, Region III. Reported contract value: ₱74,250,000.00. Status: Reported complete (DPWH). Contractor on record: J H R ENT. Figures trace to sumbong.

PANIQUI (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River Control ( Right Dike ) , Villa Paz - Dicolor Section, Gerona, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018106

₱90,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008257

₱1,904,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008259

₱176,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱74,250,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

September 5, 2024