Construction of Flood Mitigation Structure23IF0070

Construction of Flood Control, San Antonio Creek, Ormoc City

Construction of Flood Control, San Antonio Creek, Ormoc City is a DPWH-tracked public work in ORMOC CITY (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,849,298.66. Status: Reported complete (DPWH). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to sumbong.

ORMOC CITY (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, San Antonio Creek, Ormoc City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 4th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱48,849,298.66

Progress

Reported complete (DPWH)

Start Date

April 20, 2023

Target End

October 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.