Roads21NE0087

CONCRETING OF P-2 TO P-1, BRGY. VILLA PANTINOPLE FMR PHASE II, BRGY. VILLA PANTINOPLE, BASILISA, DINAGAT ISLANDS

CONCRETING OF P-2 TO P-1, BRGY. VILLA PANTINOPLE FMR PHASE II, BRGY. VILLA PANTINOPLE, BASILISA, DINAGAT ISLANDS is a DPWH-tracked public work in Dinagat Islands DEO, Region XIII. Reported contract value: ₱24,825,008.18. Status: Reported complete (DPWH). Contractor on record: CARTESIAN BUILDERS CORP FORMERLY: CARTESIAN BUILDERS. Figures trace to dpwh.

Dinagat Islands DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Protecting Do±a Helene Br. II, Basilisa, Dinagat Islands
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Dinagat Islands DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

169 projects · ₱2.8B total · 4 flags

4. Implementation

Contract Amount

₱24,825,008.18

Progress

Reported complete (DPWH)

Start Date

August 20, 2021

Target End

May 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.