Roads21M00029

CONSTRUCTION OF CONCRETE ROAD, JCT. SURALLAH-LAKE SEBU--MAITUM ROAD LUHIB - LAMFUGON-TASIMAN BYPASS ROAD, STA. 0+000-STA. 4+140

CONSTRUCTION OF CONCRETE ROAD, JCT. SURALLAH-LAKE SEBU--MAITUM ROAD LUHIB - LAMFUGON-TASIMAN BYPASS ROAD, STA. 0+000-STA. 4+140 is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱135,099,980.59. Status: Reported complete (DPWH). Contractor on record: 3 K'S INDUSTRIAL MAINTENANCE AND SERVICES INC. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱135,099,980.59

Progress

Reported complete (DPWH)

Start Date

May 31, 2021

Target End

July 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.