GAA 2025 SSP25KI0059

BASIC INFRASTRUCTURE PROGRAM-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PUROK 4 TO PUROK 6, BARANGAY DULLAN, ALORAN, MISAMIS OCCIDENTAL.

BASIC INFRASTRUCTURE PROGRAM-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PUROK 4 TO PUROK 6, BARANGAY DULLAN, ALORAN, MISAMIS OCCIDENTAL. is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱4,942,350.11. Status: Past target date (DPWH On-Going). Contractor on record: DDS BUILDERS. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Aloran River, Aloran, Misamis Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Misamis Occidental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

262 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱4,942,350.11

Progress

Past target date (DPWH On-Going)

Start Date

June 22, 2025

Target End

September 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.