Construction of Flood Mitigation Structure24ID0039

Construction of Flood Control Structure, Barangay 1, Jaro, Leyte

Construction of Flood Control Structure, Barangay 1, Jaro, Leyte is a DPWH-tracked public work in JARO (LEYTE), LEYTE, Region VIII. Reported contract value: ₱4,862,639.81. Status: Reported complete (DPWH). Contractor on record: IVS BUILDERS. Figures trace to sumbong.

JARO (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay 1, Jaro, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008522

₱1,477,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0004418

₱503,725.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008526

₱136,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,862,639.81

Progress

Reported complete (DPWH)

Start Date

March 15, 2024

Target End

September 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.