Flood Control and Drainage18LE0048

CONSTRUCTION OF CONCRETE REVETMENT (RC CUT-OFF WALL) INCLUDING RROW, BITON, DON MARCELINO, DAVAO OCCIDENTAL (STA. 0 + 000 -STA. 0 + 300)

CONSTRUCTION OF CONCRETE REVETMENT (RC CUT-OFF WALL) INCLUDING RROW, BITON, DON MARCELINO, DAVAO OCCIDENTAL (STA. 0 + 000 -STA. 0 + 300) is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱9,676,383.80. Status: Reported complete (DPWH). Contractor on record: FORTSTONE CONST ENT. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment (RC Cut-off Wall), Biton, Don Marcelino, Davao Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,676,383.80

Progress

Reported complete (DPWH)

Start Date

June 25, 2018

Target End

October 31, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.