Roads24PB0029

CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER RA 11239, INSTALLATION OF TRAFFIC SIGNAGE ALONG CONNER-KABUGAO ROAD-K0566+081-K0589+156, CONNER AND KABUGAO, APAYAO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER RA 11239, INSTALLATION OF TRAFFIC SIGNAGE ALONG CONNER-KABUGAO ROAD-K0566+081-K0589+156, CONNER AND KABUGAO, APAYAO is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,292,779.64. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: GKA ENGINEERING AND CONST. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Apayao River Flood Control, Sta. 77 + 847 - Sta. 78 + 221 ( R / S ) , Apayao
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Apayao 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

58 projects · ₱595.3M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTI-PURPOSE/ FACILITIES, CONSTRUCTION (COMPLETION) OF DPWH BUILDING APAYAO 1ST DISTRICT ENGINEERING OFFICE, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2023₱38.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, ABBUT-CONNER RD-K0548+630-K0548+702

Apayao 1st DEO, Cordillera Administrative Region

2025₱27.2M
Past target date (DPWH On-Going)
No sat.

Construction of Barren River (Downstream) Flood Control along Chico River Basin, Sta. 37 + 414 - Sta. 37 + 664 (R/S), Barangay Paddaoan, Conner, Apayao

CONNER (APAYAO), APAYAO, Cordillera Administrative Region

2023₱24.5M
Reported complete (DPWH)
No sat.

PACKAGE I: ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE (SECONDARY ROADS) KABUGAO-PUDTOL-LUNA-CAGAYAN ROAD, 1.) K0623+446-K0624+112, 2.) K0626+(-072)-K0626+(-006), 3.) K0626+278-K0626+331(RS),

Apayao 2nd DEO, Cordillera Administrative Region

2019₱21.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, CONNER-KABUGAO RD- K0581+090-K0581+319

Apayao 1st DEO, Cordillera Administrative Region

2023₱19.6M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 1: CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUND: CONSTRUCTION OF 2STY6CL WITH LABORATORY, CONNER NATIONAL HS, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱19.4M
Past target date (DPWH On-Going)
View all 58 projects →

4. Implementation

Contract Amount

₱4,292,779.64

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 8, 2024

Target End

May 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.