Construction of Flood Mitigation Structure24FK0047

Construction of Flood Mitigation Structure along Salvador H. Escudero III, Sorsogon River Downstream, Sorsogon City, Sorsogon

Construction of Flood Mitigation Structure along Salvador H. Escudero III, Sorsogon River Downstream, Sorsogon City, Sorsogon is a DPWH-tracked public work in CITY OF SORSOGON (CAPITAL) (SORSOGON), SORSOGON, Region V. Reported contract value: ₱49,499,971.87. Status: Reported complete (DPWH). Contractor on record: AREMAR CONST CORP. Figures trace to sumbong.

CITY OF SORSOGON (CAPITAL) (SORSOGON), SORSOGON, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Salvador H. EscudeRO 2I, Sorsogon River Downstream, Sorsogon City, Sorsogon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010971

₱1,942,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0007665

₱695,191.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010972

₱179,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

161 projects · ₱12.0B total · 2 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA(LZ), SECTION C:K0585+431-K0588+170.00 (W/ EQUATIONS);SECTION D: SECTION D:K0588+370.00-K0590+181.00(W/ EQUATIONS); SECTION E

Region V, Region V

2018₱289.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER II:I-BARCELONA-CASIGURAN DIVERSION ROAD,BARCELONA SECTION,SORSOGON;II-JUBAN-BULAN DIVERSION ROAD,BULAN SECTION,SORSOGON;III-

Region V, Region V

2021₱241.9M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER I-I-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 7, SORSOGON;II-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 8, SORSOGON, SORSOG

Region V, Region V

2021₱211.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SORSOGON CITY COASTAL BY-PASS ROAD, PACKAGE 6, SORSOGON, SORSOGON CITY, SORSOGON (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2020₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BALOGO SPORT COMPLEX SORSOGON CITY

Sorsogon DEO, Region V

2020₱192.7M
Reported complete (DPWH)
No sat.

ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 19, SORSOGON

Sorsogon DEO, Region V

2025₱141.4M
Past target date (DPWH On-Going)
View all 161 projects →

4. Implementation

Contract Amount

₱49,499,971.87

Progress

Reported complete (DPWH)

Start Date

May 17, 2024

Target End

December 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.