Roads20CH0009

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF PAVED ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVENUE (JASA) RD - K0076+669 - K0077+160, K0077+410 - K0077+775, K0078+678 - K0079+021, GUAGUA, PAMPANGA

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF PAVED ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVENUE (JASA) RD - K0076+669 - K0077+160, K0077+410 - K0077+775, K0078+678 - K0079+021, GUAGUA, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱53,067,982.26. Status: Reported complete (DPWH). Contractor on record: OMICRON CONST INC FORMERLY: OMICRON CONST. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Porac River, Jalung, Pampanga
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Pampanga 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

51 projects · ₱1.6B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS OF JOSE ABAD SANTOS AVENUE (JASA) K0081+660-K0082+190, K0081+000-K0081+660, K079+790-K0081+000, LUBAO AND GUAGUA, PAMPANGA

Pampanga 2nd DEO, Region III

2019₱96.5M
Reported complete (DPWH)
No sat.

BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - VALDEZ BR. (B01522LZ) ALONG SN ANTONIO-FLORIDABLANCA RD., FLORIDABLANCA, PAMPANGA

Pampanga 2nd DEO, Region III

2023₱96.5M
Reported complete (DPWH)
No sat.

BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - CAULAMAN BR. (B01529LZ) ALONG ANGELES-PORAC-FLORIDABLANCA-DINALUPIHAN RD, FLORIDABLANCA, PAMPANGA

Pampanga 2nd DEO, Region III

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - K0080+240 - K0081+448, K0082+951.58 - K0083+348.43, GUAGUA AND LUBAO, PAMPANGA

Pampanga 2nd DEO, Region III

2021₱72.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS ALONG SAN ANTONIO-FLORIDABLANCA ROAD K0081+(-950) - K0081+(-885), K0081+(-869)-K0081+(-136), K0085+700-K0086+930, K0089+136-K0089+871, GUAGUA - FLORIDABLANCA, PAMPANGA

Pampanga 2nd DEO, Region III

2018₱67.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) K0076+728.56-K0077+159.69, K0077+410-K0077+651.00, K0078+280.00-K0078+448.50, L0079+495.00-K0079+613.50, K0079+790.00-K0080+240.00, K0087+197.00-K0087+231.00. K0094

Pampanga 2nd DEO, Region III

2021₱54.0M
Reported complete (DPWH)
View all 51 projects →

4. Implementation

Contract Amount

₱53,067,982.26

Progress

Reported complete (DPWH)

Start Date

December 1, 2020

Target End

July 28, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.