Buildings and Facilities22DH0026

REHABILITATION OF ADMINISTRATION/PLANNING BUILDING, DPWH -LAGUNA I DEO, STA. CRUZ, LAGUNA

REHABILITATION OF ADMINISTRATION/PLANNING BUILDING, DPWH -LAGUNA I DEO, STA. CRUZ, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱4,850,911.16. Status: Reported complete (DPWH). Contractor on record: POWER K CONST SUPPLY. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall (Staggered), Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Laguna 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

345 projects · ₱6.8B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, DOH REGION IV-A OFFICE, LIPA CITY

Batangas 4th DEO, Region IV-A

2023₱144.1M
Reported complete (DPWH)
No sat.

LOCALLY-FUNDED PROJECTS, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF DEPARTMENT OF HEALTH REGION 4A REGIONAL OFFICE MARAWOY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS CASILE - TAGAYTAY ROAD, PACKAGE C, LAGUNA

Region IV-A, Region IV-A

2024₱118.1M
Ongoing (DPWH-reported)

CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMENT OF TRIBUTARY CREEK AS OUTFALL OF THE DETENTION POND AT BRGY. MAMPLASAN LEADING TO CARMONA-BIÑAN RIVER, BIÑAN CITY, LAGUNA

Region IV-A, Region IV-A

2020₱115.7M
Reported complete (DPWH)
No sat.

SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2025₱111.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2021₱101.3M
Reported complete (DPWH)
View all 345 projects →

4. Implementation

Contract Amount

₱4,850,911.16

Progress

Reported complete (DPWH)

Start Date

March 22, 2022

Target End

October 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.