Flood Control and Drainage16CK0209

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG MARIMLA RIVER, LEFT BANK, BAMBAN, TARLAC

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG MARIMLA RIVER, LEFT BANK, BAMBAN, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱45,615,892.25. Status: Reported complete (DPWH). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Moriones River, Left Side, Tibagan Section, Tibagan, Tarlac City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0006984

₱55,000,000.00 · FY2017

Released to University of Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱45,615,892.25

Progress

Reported complete (DPWH)

Start Date

April 17, 2017

Target End

September 10, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.