GAA 2017 MFO-117L00096

CONST./OPENING/CONC. OF MAWAB-MARAGUSAN-CARAGA RD,SITIO TAGDALONGDONG-BRGY. LANGAWISAN SECT. INCL. C

CONST./OPENING/CONC. OF MAWAB-MARAGUSAN-CARAGA RD,SITIO TAGDALONGDONG-BRGY. LANGAWISAN SECT. INCL. C is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱287,499,988.51. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱287,499,988.51

Progress

Reported complete (DPWH)

Start Date

April 24, 2017

Target End

December 28, 2018

5. Audit