Roads16M00021

ROAD WIDENING OF MIDSAYAP-MARBEL ROAD, K1770+(904)-K1772+835; K1772+850-K1772+873; 1773+513-K1773+720, TANTANGAN, SOUTH COTABATO

ROAD WIDENING OF MIDSAYAP-MARBEL ROAD, K1770+(904)-K1772+835; K1772+850-K1772+873; 1773+513-K1773+720, TANTANGAN, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱90,396,767.69. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱90,396,767.69

Progress

Reported complete (DPWH)

Start Date

May 30, 2016

Target End

June 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.