Roads25CJ0128

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TARLAC CITY NORTHWESTERN ALTERNATE ROUTE (SAN ISIDRO - AGUSO), (PHASE 8), TARLAC

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TARLAC CITY NORTHWESTERN ALTERNATE ROUTE (SAN ISIDRO - AGUSO), (PHASE 8), TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱92,930,897.18. Status: Past target date (DPWH On-Going). Contractor on record: R R RICAFORT CONST AND SUPPLIES. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay San Miguel - Sta. Maria, San Manuel, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tarlac DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱92,930,897.18

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

September 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.