Roads22AB0107

CONSTRUCTION (COMPLETION) OF ROAD, SITIO ANONANGAN BRGY. SAN LORENZO, SAN NICOLAS, ILOCOS NORTE

CONSTRUCTION (COMPLETION) OF ROAD, SITIO ANONANGAN BRGY. SAN LORENZO, SAN NICOLAS, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱4,899,977.74. Status: Reported complete (DPWH). Contractor on record: MEGAPOLITAN BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Brgy. Santiago, Solsona, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

354 projects · ₱7.2B total · 6 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SRIP AND ITS APPURTENANT STRUCTURE, CABANGARAN SRIP, BARANGAY CABANGARAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱149.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 2, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 1, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, BARANGAY MABALENG, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱122.7M
Past target date (DPWH On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAOIT RIVER DIVERSION CANAL, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱115.8M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF SWIP, BARANGAY CAMANDINGAN, CITY OF BATAC, ILOCOS NORTE

Region I, Region I

2025₱112.3M
Past target date (DPWH On-Going)
View all 354 projects →

4. Implementation

Contract Amount

₱4,899,977.74

Progress

Reported complete (DPWH)

Start Date

March 25, 2022

Target End

May 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.