Roads23PJ0049

23PJ0049: REPAIR/REHABILITATION ANDCONSTRUCTION OF FARM-TO-MARKET ROADS IN DESIGNATED KEY PRODUCTIONAREAS-CONCRETING OF SITIO LUPAO FMR, BRGY. JACMAL, AGUINALDO, IFUGAO

23PJ0049: REPAIR/REHABILITATION ANDCONSTRUCTION OF FARM-TO-MARKET ROADS IN DESIGNATED KEY PRODUCTIONAREAS-CONCRETING OF SITIO LUPAO FMR, BRGY. JACMAL, AGUINALDO, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱11,940,000.00. Status: Reported complete (DPWH). Contractor on record: JLY CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱39,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Lamut River, Sta. 18 + 300 - Sta. 18 + 850 (Lawig Side), Lamut, Ifugao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ifugao 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23PJ0049 Repair/Rehabilitation and Construction o

₱11,928,083.30 · JLY CONSTRUCTION

Contractor

27 projects · ₱526.0M total · 1 flags

Other projects by this contractor

No sat.

25PJ0010: ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS-ALFONSO LISTA-AURORA BDRY RD - K0445 + 765 - K0446 + 735, K0446 + 775 - K0447 + 282

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱78.5M
Past target date (DPWH On-Going)
No sat.

24PJ0016: NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS AGUINALDO - TOBOY - NATONIN ROAD, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱52.1M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - NUEVA VIZCAYA-IFUGAO-MT PROVINCE RD - K0340 + 000 - K0341 + 000, BANAUE, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2022₱41.2M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS NEW ROADS-AGUINALDO TOBOY NATONIN ROAD, IFUGAO STA. 4+200-STA 5+129, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱39.2M
Reported complete (DPWH)
No sat.

25PJ0012: ASSET PRESERVATION PROGRAM-CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS -SECONDARY ROADS-BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD - K0398 + 033 - K0398 + 130, K0398 + 481 - K0398 + 593, K0399 + 032 - K0399 + 503, K0400

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱32.2M
Past target date (DPWH On-Going)
No sat.

25PJ0008: ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS-BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD - K0406 + 820 - K0406 + 859, K0409 + 586 - K0409 + 637, K0410 + 359 - K0410 +

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱23.3M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱11,940,000.00

Progress

Reported complete (DPWH)

Start Date

June 26, 2023

Target End

September 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.