Construction of Flood Mitigation Structure23CG0068

Construction of Matubig Creek, Sta Ana, Pampanga

Construction of Matubig Creek, Sta Ana, Pampanga is a DPWH-tracked public work in SANTA ANA (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱37,239,843.68. Status: Reported complete (DPWH). Contractor on record: CHOLO CONST AND TRADING. Figures trace to sumbong.

SANTA ANA (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

139 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION AT SAN ROQUE BITAS CREEK, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱91.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT PALINLANG CREEK, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱91.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONCRETING OF SLOPE PROTECTION AT INUMAN BAKA STA. ANA-ARAYAT PORTION, PAMPANGA PHASE II

Pampanga 1st DEO, Region III

2025₱91.5M
Past target date (DPWH On-Going)

Rehabilitation of River Channel and Construction of Concrete Slope Protection, Malisik R.C., Candaba, Pampanga

CANDABA (PAMPANGA), PAMPANGA, Region III

2022₱82.1M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BALIWAG - CANDABA - STA. ANA RD. - K0067+433 - K0067+571, CANDABA, PAMPANGA

Pampanga 1st DEO, Region III

2019₱67.9M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONCRETING OF SLOPE PROTECTION AT INUMAN BAKA STA. ANA-ARAYAT PORTION, PAMPANGA PHASE I

Pampanga 1st DEO, Region III

2025₱64.2M
Past target date (DPWH On-Going)
View all 139 projects →

4. Implementation

Contract Amount

₱37,239,843.68

Progress

Reported complete (DPWH)

Start Date

March 22, 2023

Target End

October 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.