Roads22K00329

CONST. OF BY-PASS AND DIVERSION ROADS, JCT. BUDA, QUEZON -JCT. VALENCIA- TALAINGOD ROAD-KALAGANGAN, SAN FERNANDO ALTERNATE/BY PASS ROAD, PACKAGE 19, BUKIDNON

CONST. OF BY-PASS AND DIVERSION ROADS, JCT. BUDA, QUEZON -JCT. VALENCIA- TALAINGOD ROAD-KALAGANGAN, SAN FERNANDO ALTERNATE/BY PASS ROAD, PACKAGE 19, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱70,692,777.88. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC 17267. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱70,692,777.88

Progress

Reported complete (DPWH)

Start Date

June 6, 2022

Target End

April 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.