Buildings and Facilities17IB0017

CONSTRUCTION OF TWO-STOREY OFFICE BUILDING (DPWH STANDARD DESIGN) EASTERN SAMAR DISTRICT ENGINEERING OFFICE, BORONGAN CITY, EASTERN SAMAR.

CONSTRUCTION OF TWO-STOREY OFFICE BUILDING (DPWH STANDARD DESIGN) EASTERN SAMAR DISTRICT ENGINEERING OFFICE, BORONGAN CITY, EASTERN SAMAR. is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱34,410,250.56. Status: Reported complete (DPWH). Contractor on record: JQD CONST & GEN SERVICES. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,317,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control along Borongan River protecting Borongan-Guiuan Road (K0936+463 - K0937+009), Borongan City, Eastern Samar
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0013214

₱179,017.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

14 projects · ₱673.4M total · 4 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS/MAASIN CITY COASTAL BYPASS ROAD, INCL. SLOPE PROTECTION, SOUTHERN LEYTE (CONSTRUCTION OF CONCRETE ROAD AND CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE)MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2018₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS / MAASIN CITY COASTAL BYPASS ROAD, SOUTHERN LEYTE, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2021₱77.2M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - BDRY. SO. LEYTE - MAASIN - MACROHON - SOGOD - JCT. DAANG MAHARLIKA RD. - ALONG MAASIN CITY SECTION

Southern Leyte 1st DEO, Region VIII

2024₱61.7M
Reported complete (DPWH)
No sat.

CONST. OF M/P BLDG FOR THE PHILIPPINE FIBER INDUSTRY DEV'T. AUTHORITY (PHILFIDA) BLDG, BRGY. TALON 2

Las Piñas-Muntinlupa DEO, National Capital Region

2019₱57.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - MULTI-PURPOSE BUILDING / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF LEGISLATIVE BUILDING, TOMAS OPPUS, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱49.5M
Reported complete (DPWH)
No sat.

Construction of Canturing Flood Structures, Canturing River, Maasin City, Southern Leyte

CITY OF MAASIN (CAPITAL) (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII

2023₱49.0M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱34,410,250.56

Progress

Reported complete (DPWH)

Start Date

March 13, 2017

Target End

December 7, 2017

5. Audit